LNG power projects face multiple hurdles
vietnamnews - 1/7/2025 11:15:06 AM
 (0 ratings. You must sign in to rate.)

LNG power projects in Vietnam are currently grappling with many obstacles, ranging from bureaucratic delays to issues with power purchase agreements (PPAs), leading to significant slowdowns.

 

A LNG power facility in the central province of Nghệ An. VNA/VNS Photo

LNG power projects in Vietnam are currently grappling with many obstacles, ranging from bureaucratic delays to issues with power purchase agreements (PPAs), leading to significant project implementation slowdowns.
 
The Southeast Asian economy considers the development of LNG power a matter of national energy security. According to Decision 500/QĐ-TTg, LNG power is expected to account for 14.9 per cent of total power capacity, supplying 83 billion kWh by 2030.
 
However, the implementation of these projects faces numerous hurdles.
 
Challenges
 
Lã Hồng Kỳ from the State Steering Committee Office for Energy Projects emphasised that these critical LNG power projects face various challenges that need to be resolved.
 
Kỳ highlighted that several provinces, such as Thanh Hóa, Nghệ An, and Ninh Thuận, have yet to select investors, due to delays in investment policy approval and tendering processes. Additional challenges include land clearance, adjustments to local planning, land handover and leasing for project sites and transmission lines required to synchronise power evacuation.
 
For approved investors, securing financing remains a major challenge.
 
Most LNG power projects, except Nhơn Trạch 3 and 4, rely entirely on PPAs to obtain loans. However, none of the LNG power projects have successfully negotiated or signed PPAs with EVN (Vietnam Electricity) due to unresolved issues, including concerns over the stability of long-term energy quantity under contract (QC), transferring gas purchase commitments into power purchase agreements and aligning gas pricing mechanisms with electricity pricing.
 
Foreign investors also demand additional government guarantees, such as foreign currency conversion guarantees, payment guarantees, contract termination assurances with EVN and guarantees against delays in transmission line construction, he said.
 
According to Kỳ, synchronisation is vital for the success of LNG project chains. Yet, these projects are often subject to numerous uncontrollable external factors, prolonged timelines, technological and policy risks, involvement of multiple stakeholders, and a complex legal environment involving multiple laws. These challenges increase costs and project durations and create significant barriers for investors.
 
To ensure timely project implementation, he said the country must establish mechanisms and policies to address the outlined challenges and identify an appropriate energy structure.
 
Reforms
 
Nguyễn Đức Tùng from the Institute for Strategic Research and Industrial Policy proposed reviewing and refining the legal and management frameworks for LNG power projects. This involves amending regulations within Vietnam's Investment Law, Bidding Law, Construction Law, Environmental Law and Planning Law to streamline project implementation. He added that clear and practical policies are essential to ensure effective management, build market access and distribution systems, and foster international cooperation.
 
He emphasised the importance of a dual strategy combining domestic gas exploration with imports to maintain a stable and long-term LNG supply. Prioritising the exploration and development of new gas fields will not only reduce dependence on imports but also unlock domestic resource potential.
 
Over the longer term, the country should explore the feasibility of establishing LNG production facilities, provided adequate technological, financial, and human resources are available.
 
Vietnam should also implement mechanisms for LNG imports and strategically position LNG power plants nationwide to minimise transportation costs and enhance fuel absorption efficiency. Additionally, transferring LNG pricing into electricity pricing within PPAs is fundamental to ensuring the economic viability and attractiveness of LNG power investments.
 
The country has identified 13 LNG power projects as critical infrastructure and approved by the Prime Minister. — VNS
 
 
Read original article here
Newer News
21/04 US tariffs prompt Việt Nam’s supply chain shift
21/04 Việt Nam stays on course for 8 per cent growth despite tariff risks
14/04 EU applies provisional anti-dumping measures on hot-rolled steel imports from Việt Nam
09/04 FTA Index is key driver to implement free trade agreements
09/04 CPI rises 3.22%, inflation remains under control in Q1
09/04 Deputy PM urges diplomatic measures conducive to US trade policy adjustments
09/04 AmCham Việt Nam speaks out on new US reciprocal tariffs
05/04 Vietnamese Party chief holds phone talks with US President
04/04 Hà Nội keeps CPI well under control
04/04 Việt Nam's foreign investment surges 35% in Q1
Older News
07/01 2025 GDP growth target: ambitious and challenging
06/01 Nearly 76,180 enterprises resume operations in 2024
06/01 The bright prospects of Việt Nam's asset management industry
06/01 Small and medium-sized enterprises focus on CSR practices
06/01 Leather, footwear industry aims to gain export growth of 10% in 2025
03/01 Experts highlight challenges for this year
03/01 Smart manufacturing still in early stages
03/01 According to Statista, Vietnam’s outsourcing market is projected to reach a value of nearly US$698 million this year.
03/01 Vietnam PMI stands at 49.8 in December
02/01 Vietnam set to become regional manufacturing tech hub this year
 
Newsletter Signup
Top Stories
Việt Nam to launch KRX trading system on May 5
Profits, dividends, capital increases and bad debts on agendas of 2025 banking AGMs
Stock market showed weakest Q1 in 3 years
VND: VNDirect to divest from Goldsun Food
Market cautious as liquidity drops significantly
Market Update
Last updated at 3:10:00 PM
VN-INDEX 1,229.23 +5.88/+0.48%
Real-time chart
Top 5 Actives
Top 5 Gainers
Top 5 Losers
My Favorite Quotes
Company Research
Type in the symbol above for thorough background information, key statistics and financial information.
Stock Sectors
We continuously improve our services, here are the latest updates...
Portfolio
Allow you to monitor a customised group of securities. You can set up multiple Portfolios to help you better manage your investments.
Trigger Alerts
Get up-to-date alerts delivered directly to your email address.
Stock Screener
Allow you to filter the market and find exactly what sort of company you are looking for.
Live Terminal
Get instant access to FREE REAL-TIME streaming quotes for hundreds of stocks from HOSE, HNX and UPCOM exchanges.